Schedule Assessment - What is it, Who are the DCMA and How are they done?
Updated: Sep 11, 2021

DCMA 14-point Schedule Assessment is a project management guideline based on 14 metrics to make a qualitative and quantitative evaluation of a schedule. It is a handbook developed by the Defense Contract Management Agency (DCMA) for the Defense Industry.
Making an assessment of the schedule is essential for the planning, monitoring, and controlling of a project. Therefore, these points are crucial for the health of the project schedule to identify and analyze areas that are critical and may cause issues and obstruct the schedule.
Who are the DCMA?
The Defense Contract Management Agency (DCMA) is a Division of the Department of Defense (DoD) that is responsible for ensuring that DoD suppliers deliver supplies and services on time and at the agreed cost. The DCMA has duties before and after the contract is awarded. After the contract is awarded, DCMA monitors the contractors’ deliverables to make sure that the expenditures, project execution, and schedules are in compliance with the contract.
What are the DCMA’s 14 Schedule Assessment Metrics?
These metrics may be a starting point of discussion between the agency and the contractor regarding the project that may lead to a better understanding of the contractor’s approach to the project.
DCMA has implemented a set of Tripwire metrics that are used by OSD (Office of the Secretary of Defense) as part of its assessment.
DCMA provides its contractors with a spreadsheet to perform the calculations necessary to derive metrics.
Being involved in a project that will be reviewed using these tripwires, requires either submittal of a schedule that does not violate the metrics’ thresholds as a contractor - or - for it to be reviewed with a construction manager.
In both cases, the schedule must be ready for the 14-point schedule assessment.
The following are the 14-point schedule assessment checks:
1. Logic Check
2. Leads Check
3. Lags Check
4. Relationship Types Check
5. Hard Constraints Check
6. High Float Check
7. Negative Float Check
8. High Duration Check
9. Invalid Dates Check
10. Resources Check
11. Missed Tasks Check
12. Critical Path Test Check
13. Critical Path Length Index (CPLI)
14. Baseline Execution Index (BEI)
Let’s have a look in more detail:
Logic
The metric ‘Logic’ is a means to open the possibility for measurement of the ‘%’ of incomplete tasks with no predecessors and/or successors, also called ‘dangling’ activities.
For this metric, it is preferable that the number of unfinished activities missing predecessors and/or successors don’t exceed 5%.
The best practice for avoiding incompleteness of tasks is ensuring that every task has at least one finish-to-start or start-to-start relation as its predecessor and at least one finish-to-start or finish-to-finish as its successor.
This metric is important in investigating how project tasks are connected to each other and in looking to assure that no incomplete tasks affect the project schedule negatively.
Leads
‘Leads’ is the control criteria that helps measure the ‘%’ of tasks that have a negative lag between each other.
In particular, the term designates the overlapping time between two activities in the project schedule. In other words, it indicates the exact time (days) that would be overlapped if a task starts a certain time before the finish date of its predecessor.
The leads in the schedule should equal zero, therefore there shouldn’t be tasks with a negative lag between each other. If there is a part of the schedule, which could prove itself as a potential problem, the tasks in question should be decomposed into separate tasks. This metric can impede the critical path analysis, therefore it is preferable that it is used within the limits.
Lags
The metric ‘Lags’ is the opposite of ‘Leads’. Specifically, it allows an evaluation of the ‘%’ of project activities that have a positive lag between each other. The metric actually indicates the time (hours/days) calculated when a certain activity starts after the finish date of its predecessor.
The DCMA threshold for this metric is more flexible than the one for the Leads and it advises that the lags in the project schedule shouldn’t be greater than 5%. However, the excessive use of lags as well may cause an obstruction to the critical path analysis.
Therefore it is recommended that they are avoided altogether.
A good practice for this metric is to present activities with specific names rather than with an ‘X-days lag’.
Relationship Types
It is recommended that 90% of the project schedule activities are of a finish-to-start type (FS). The finish-to-start type of relationship stands for ‘Activity A must be completed before activity B can begin’. This type of relationship between particular tasks is the foundation of the Waterfall method used in project management.
Finish-to-start relationship provides the most explicit presentation of the project schedule activities. The other types of relationships, which can be identified in a schedule, are finish-to-finish (FF), start-to-start (SS), and start-to-finish (SF). However, it is not recommendable for these to be used since they are harder to monitor and control.
Hard Constraints
Under ‘Constraints’ in a project schedule are identified Hard Constraints (Mandatory Start and Mandatory Finish) and Soft Constraints (As Late As Possible, Start On, Start On or Before, Start On or After, Finish On, Finish On or Before and Finish On or After).
DCMA recommends 5% of the constraints used to be Hard Constraints - because they may provoke problems in the schedule.
Hard Constraints may prevent the schedule from being logic-driven and create negative lags.
In other words, Hard Constraints should be avoided since they can obstruct the logic of flowing naturally.
Soft Constraints, on the other hand, allow the schedule to be logic-driven and they are not critical to the schedule.
High Float
This metric measures the ‘%’ of unfinished tasks with total float greater than 44 working days. DCMA requires that the High Float activity doesn’t exceed 44 working days, i.e. the percentage of total incomplete tasks doesn’t exceed 5%.
This metric represents the time (hours/days) that an activity can be delayed without negatively affecting project milestones and/or the estimated time for project completion.
A certain task with a total float that exceeds 44 working days could be a consequence of incomplete activities (predecessor/successor).
Negative Float
This metric is interconnected with Hard Constraints since it may indicate that Hard Constraints have been assigned to the schedule. When this happens, it is very much feasible that the project's or milestones' completion is delayed.
DCMA threshold for this metric is zero, therefore it is required that regular checks and reviews of the project schedule are executed. The Negative Float, or Slack, should be avoided, and, if tasks with a large amount of negative float are noticed, they should be mitigated or otherwise, the risk for a missing project or milestones deadlines could arise.
High Duration
This metric may help open the possibility to monitor and control the duration of tasks and it requires that no task should last longer than 44 working days. If it is detected that the percentage of incomplete tasks with a duration beyond 44 days is above 5% it is preferable to examine if it is possible to decompose them in distinct tasks.
Breaking down activities helps them to be measurable and controllable.
Tasks with high duration could create obstacles in the project schedule and progress and deform the critical path.
Invalid Dates
The metric for Invalid Dates analyses both forecast and actual dates of project activities.
An activity is considered to have invalid dates if it has forecast start/finish dates in the past or actual start/finish dates in the future. More specifically, this metric refers to tasks with actual start/finish date after project status date and with start/finish date before project status date without an actual start/finish.